Data Center Standby Generator Fuel System Flushing
Frontline Global Services, an Astro Pak Company, cleaned fuel oil piping serving standby generators at a data center. The newly installed system contained construction-related contamination that needed to be removed before the generator fuel systems were placed into service.
Challenge
Initial inspections found significant debris in the fuel oil piping. Flushing the system required a way to remove that contamination without carrying it into the downstream generator equipment. The size and configuration of the piping also made it necessary to maintain effective flow velocity throughout the cleaning process.
Solution
Frontline engineered and installed a temporary return manifold to create a controlled flow path and direct contaminants away from the generator fuel systems. The team divided the work into phases, isolating sections of piping to maintain the velocity needed for effective flushing.
Proving screens and ISO particle counts were used throughout the project to monitor progress and verify cleanliness.
Outcome
Final testing met or surpassed the project’s required cleanliness specifications. Frontline turned over a verified clean fuel oil piping system for generator commissioning and completed the work with a 100% safety record.
On-Site